Approximately fifteen months after approval in June 2025, 4.2 million dollars had been disbursed. The LEAP project, designed to finance basic services and reconstruction following the 2024 destructions, was supposed to disburse 100 million by July 2026: the World Bank’s September monitoring counted less than one-twentieth of that amount. The World Bank identifies strong institutional and fiduciary constraints, without establishing that the gap stems exclusively from the state rather than from donors.

The essentials

  • Of the 100 million expected in Lebanon by July 2026 under the LEAP project, only 4.2 million had been disbursed in September, according to World Bank monitoring reported by Associated Press.
  • The World Bank approved 250 million dollars for this project; reconstruction and recovery needs are estimated at 11 billion.
  • Administrative constraints rank among several risk factors affecting execution: issuing a public contract, controlling an expenditure, and processing a payment all require functioning institutions.
  • Similar administrative constraints are found in other reconstructions funded by international donors.
  • Prior investment in execution capacities appears necessary to transform aid promises into infrastructure and services.

A disbursement rate of 4%

The raw figure deserves to be placed in context. The World Bank approved 250 million dollars for LEAP on June 24, 2025. It anticipated 100 million in actual disbursements by July. By the end of September, only a reduced share of anticipated disbursements had been paid out. The World Bank estimates recovery and reconstruction needs at 11 billion dollars in its RDNA assessment conducted with technical partners.

These three figures do not compare mechanically: the 250 million approved covers only a fraction of an overall need of an entirely different magnitude. But the relationship between what was expected and what was paid says something precise: financial commitments have no bearing on ground reality.

The World Bank distinguishes in particular between approval, signature, entry into force, and actual disbursements. Disbursement occurs during execution: money leaves the donor’s coffers because a contract has been issued, an invoice presented, an expenditure controlled. Project closure and completion follow. Each of these stages requires an administration capable of accomplishing them. In Lebanon, this administration exists formally.

The World Bank identifies execution capacity constraints and plans CDR reforms.

The limits of the Lebanese state

Lebanon is not an absent state. It has ministries, public procurement directorates, a Court of Accounts. But since the 2019 financial crisis and the Beirut port explosion in 2020, these institutions operate on Lebanese pound salaries that have lost most of their real value, staffing depleted by exile, and a governance crisis that has paralyzed appointments at all levels of the executive. Public procurement procedures, lengthy, formalized, exposed to donor audits, demand precisely what the Lebanese state has least of: qualified administrative time and minimal institutional stability.

This situation extends beyond Lebanon alone. Post-conflict and post-disaster reconstructions systematically encounter the same obstacle. In Ukraine, donors had to adapt their procedures to accelerate disbursements after February 2022, with uneven results depending on the sector. In the Sahel, funds from the Global Environment Facility and the Green Climate Fund remain mobilized for years before reaching beneficiaries, due to lack of national focal points capable of absorbing the procedures. The geography of international aid distinguishes states capable of receiving funds from those who, formally eligible, do not yet have the capacity to absorb them.

The lesson Marcel Gauchet draws from his reading of neoliberalism is useful here in a sense he did not directly explore. Gauchet observes that contemporary democracies suffer from a growing gap between formal autonomy—having rights, institutions, a budget—and the concrete capacity to exercise them. This tension, which he diagnoses in Western democracies, is found in an aggravated form in post-crisis states: political autonomy is proclaimed, institutions exist on paper, but ordinary capacity for action—issuing a contract, paying a service provider, controlling an expenditure—has collapsed. International aid then encounters a state that has the rights but not the means to exercise them.

Financing promises without effective reconstruction

Economists close to institutionalist thinking, notably Daron Acemoglu and Simon Johnson, propose a different reading. They do not speak of endogenous democratic pathology, but of capture. Lebanese institutions were durably weakened by political elites who had an interest in maintaining an administration incapable of accountability, with confessional clientelism functioning precisely because the formal state was bypassed by informal redistribution networks. On this reading, the low disbursement rate reflects a political architecture that survived the financial crisis and resists transparent reconstruction because that would shed light on flows that thrive in opacity.

The two readings do not exclude each other. The Lebanese state combines an administrative capacity deficit and institutional obstacles to reconstruction. The result is the same: contracts and payments progress at a slow rate relative to disbursement forecasts, and 4.2 million remains symbolically derisory against 11 billion in needs.

What this tension reveals for donors is uncomfortable. Europe’s economic weapon encounters the same problem at the diplomatic scale: the effectiveness of a financial instrument depends on the institutions executing it. Promising money without investing in the machinery that must transform it into services means producing political announcements, not reconstruction.

Donor choices and their blind spots

The World Bank is not unaware of these constraints. LEAP explicitly includes a capacity-building component: it finances project management units, trains public servants, and provides technical assistance. But these components often come after financial disbursements in project design, creating a vicious circle. Money is available before the administrative machinery is ready to absorb it, and disbursement delays trigger political pressure to simplify procedures, which weakens the control those same procedures were meant to guarantee.

There is an alternative documented in other contexts. World Bank assessments and the Development Assistance Committee of the Organisation for Economic Co-operation and Development suggest that prior investment in basic functions—public procurement, financial control, service provider payment—would improve absorption rates. The model is not to substitute for the beneficiary state, but to co-build with it a minimal execution capacity before financial commitments reach their ceiling.

Wales experimented with another approach: future generations commissioners charged with assessing whether public investments build sustainable capacity or are consumed in short-term spending. Transposed to the reconstruction of a post-crisis state, this principle suggests that every dollar of aid should be accompanied by an assessment of administrative capacity to absorb it, and that this assessment should condition the pace of disbursements, not justify them after the fact.

Two possible trajectories through 2035

Lebanon’s situation is not static. Two trajectories are plausible through 2035, and the signals that allow distinguishing between them are already partially observable.

In the first, donors and the Lebanese state prioritize investment in execution functions: public procurement units, financial information systems, training for public servants responsible for expenditure control. Disbursements remain slow in the first years but accelerate as administrative capacity consolidates. The absorption rate gradually catches up to commitments, and a significant fraction of the 11 billion in needs becomes verifiably covered. This trajectory requires donors to accept financing processes before results, which runs counter to their own political cycles, which reward announcements and inaugurations.

In the second, aid promises continue to be formulated at the level of needs, and the 11 billion remains a politically useful figure, without prior capacity-building being conditioned on disbursements. The gap between the 250 million approved and the few million actually paid out repeats itself for each new project. Funds remain blocked because the machinery that should absorb them is not ready. Reconstruction needs accumulate, affected populations wait, and Lebanon remains in formally financed but concretely blocked reconstruction.

The distinction between these two trajectories is read in two measurable signals. The first is the average time between approval of a public contract and the first actual payment to service providers: a shrinking timeframe indicates that administrative capacity is progressing. The second is the ratio between approved commitments and actual disbursements across all donor-funded projects, a ratio converging toward 1 indicates that aid is actually transforming into services. These signals are not spectacular. They do not make good political announcements.

But they are the only ones that say whether reconstruction is advancing or whether it is playing out in press releases.

Democratic institutions capable of lasting require precisely this patience: building ordinary, invisible, ungrateful execution capacity that transforms money into roads, into drinking water, into schools. Without it, even the best intentions of donors remain figures in spreadsheets.

Lessons from Lebanon reconstruction

The Lebanese case raises a question that international aid architectures still handle poorly. Financing instruments—approval, commitment, disbursement—were designed for states whose administrative capacity is sufficient to absorb procedures. They assume qualified public servants, functioning information systems, an intact expenditure control chain. When these conditions are absent, the financial instrument remains theoretically perfect and encounters obstacles to its execution.

Several approaches have been experimented with. Project management units shared between donors and beneficiary state make it possible to accelerate disbursements while maintaining control. But they create a symmetrical risk: if the unit substitutes for national administration instead of strengthening it, it produces short-term results without building the capacity that would allow the state to continue alone after project completion. The distinction between substitution and strengthening is a design choice made at the negotiation stage, before money is approved.

Conditioning disbursements on administrative capacity indicators rather than on physical work progress indicators is another approach. It reverses usual logic: instead of paying when the building is constructed, one first invests in the machinery that must construct it. This approach is politically harder to defend, it delays inaugurations, but technically more effective over the long term.

Lebanon is not an isolated case. It is the most documented instance of a constraint applying to any post-crisis state reconstruction. The low disbursement rate is not a scandal: it is a signal that the architecture of international aid must adapt to the reality of states facing severe administrative constraints.

The open question is whether donors are ready to reformulate their success indicators. Is a project with a slow disbursement rate but progressing local administrative capacities a success or a failure? The answer to this question will determine whether the 250 million approved for LEAP end up reaching Lebanese people who need it, or whether a next monitoring report repeats the same figures in two years.


Sources

  1. Associated Press, Lebanon reconstruction aid, September 2026, https://apnews.com/article/9c4456bac478a64c9aeff6f2fc6c84ae
  2. Marcel Gauchet, “Neoliberalism Will Not Win,” Sciences Humaines, https://www.cairn.info/revue-sciences-humaines.htm
  3. World Bank, Lebanon Emergency Assistance Project (LEAP), approval February 2026 and September 2026 monitoring, World Bank, project P180049
  4. Daron Acemoglu and Simon Johnson, Power and Progress, Basic Books, 2023
  5. Development Assistance Committee, Organisation for Economic Co-operation and Development, evaluation reports on aid absorption in fragile states